The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash Max Days
by 1 day to Crash
A 5 - $ 300 1
B 3 - $ 100 1
C 4 A $ 100 1
D 3 A $ 200 2
E 4 B $ 400 3
F 2 D, E $ 500 2
G 4 E $ 300 3
H 3 C $ 100 2
A. What is the critical path of this project?
The following table provides a description for the project Z.
Activity/ Duration/ Predecessor/ Cost to crash Max Days
by 1 day/ to Crash
A 5 - $ 300 1
B 3 - $ 100 1
C 4 A $ 100 1
D 3 A $ 200 2
E 4 B $ 400 3
F 2 D, E $ 500 2
G 4 E $ 300 3
H 3 C $ 100 2
B. What is the duration of this project?

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:40, evansh78
3× __ -2=15 7 2× __+1=7 5 7× =22 15 5× __+10=2 8 × __+4=20 6 × =10 3 × __+2=8 6 × __+8=8 9 × __+7=20 6
Answers: 3
image
Mathematics, 21.06.2019 18:30, o10889084
If 25% of y is 30, what is 60% of y?
Answers: 1
image
Mathematics, 21.06.2019 21:30, gungamer720
Aladder that is 20ft long is leaning against the side of a building. if the angle formed between the ladder and the ground is 75 degrees how far is the bottom of the from the base of the building?
Answers: 1
image
Mathematics, 21.06.2019 21:30, hammackkatelyn60
Joanie wrote a letter that was 1 1/4 pages long. katie wrote a letter that was 3/4 page shorter then joagies letter. how long was katies letter
Answers: 1
Do you know the correct answer?
The following table provides a description for the project Z. Activity Duration Predecessor Cost to...

Questions in other subjects:

Konu
Computers and Technology, 29.12.2020 01:00