The expected duration of the project (average) is 30 days and variance is 16. 1. What is the probability that the project will be completed on day 32 or earlier? 2. Suppose the official deadline for the project is 34 days. What is the probability that the project will be delayed?

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:00, rodriguezzamyy
There is an entrance to the computer room at point e which lies on ab and is 5 feet from point a. plot point e on the coordinate plane. find the distance from the entrance at point e to the printer at point e
Answers: 1
image
Mathematics, 21.06.2019 21:00, kordejah348
Sweet t saved 20 percent of the total cost of the green-eyed fleas new album let there be fleas on earth. if the regular price is $30 how much did sweet save
Answers: 1
image
Mathematics, 21.06.2019 23:20, conner87
Find the value of x in the diagram below. select the best answer from the choices provided
Answers: 1
image
Mathematics, 22.06.2019 00:00, makikorising1226
Afair survey question is one that does not encourage biased responses. which survey question is fair? a.) do you agree that only unethical people take credit for other people’s work? b.) have you ever taken credit for somebody else’s work? c.) have you ever engaged in unethical behavior, such as taking credit for somebody else’s work? d.) don’t you think it is unethical to take credit for somebody else’s work?
Answers: 1
Do you know the correct answer?
The expected duration of the project (average) is 30 days and variance is 16. 1. What is the probabi...