Mathematics, 05.06.2020 18:02, aramirez4785
At a furniture manufacturer, worker A can assemble a shelving unit in 5 hours. Worker B can assemble the same shelving unit in 3 hours. Which equation can be used to find t, the time in hours it takes for worker A and worker B to assemble a shelving unit together?
Rate
(Shelving Units per Hour)
Time
(Hours)
Fraction Completed
Worker A
One-fifth
t
Worker B
One-third
t
5 t + 3 t = 1
One-fifth t minus one-third t = 1
One-fifth t + one-third t = 1
5 t minus 3 5 = 1
Answers: 3
Mathematics, 21.06.2019 15:00, giraffegurl
Translate the word phrase into a math expression. 15 fewer than the product of 4 and a number. (pls immediately)
Answers: 2
Mathematics, 21.06.2019 18:40, banditballer2
Complete the steps, which describe how to find the area of the shaded portion of the circle. find the area of the sector by multiplying the area of the circle by the ratio of the to 360. subtract the area of the triangle from the area of the sector.
Answers: 3
Mathematics, 21.06.2019 22:20, flippinhailey
The mean of 10 values is 19. if further 5 values areincluded the mean becomes 20. what is the meanthese five additional values? a) 10b) 15c) 11d) 22
Answers: 1
At a furniture manufacturer, worker A can assemble a shelving unit in 5 hours. Worker B can assemble...
Chemistry, 17.02.2021 20:50
Mathematics, 17.02.2021 20:50
History, 17.02.2021 20:50
English, 17.02.2021 20:50
Mathematics, 17.02.2021 20:50
Health, 17.02.2021 20:50
History, 17.02.2021 20:50
Mathematics, 17.02.2021 20:50