A particular project network has two paths through it: Path A and Path B. Path A has an expected completion time of 15 weeks and a variance in completion time of 8 weeks, while Path B has an expected completion time of 16 weeks and a variance in completion time of 4 weeks. What is the probability that this project is going to take more than 18 weeks?
Answers: 2
Mathematics, 21.06.2019 18:00, RoyalGurl01
Identify which functions are linear or non-linear. a. f(x) = x2 + 1 b. f(x) = 2x + 5 c. f(x) = x 2 + 3 d. f(x) = 3 x + 7 e. f(x) = 4x + 10 2 - 5
Answers: 1
Mathematics, 21.06.2019 19:00, jthollis1348
Find the y-intercept and x-intercept for the equation 5x-3y=60 what is the y-intercept
Answers: 1
Mathematics, 21.06.2019 22:30, kaylaamberd
Maria found the least common multiple of 6 and 15. her work is shown below. multiples of 6: 6, 12, 18, 24, 30, 36, 42, 48, 54, 60, . . multiples of 15: 15, 30, 45, 60, . . the least common multiple is 60. what is maria's error?
Answers: 1
A particular project network has two paths through it: Path A and Path B. Path A has an expected com...
English, 30.11.2020 22:00