An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?

A) About 8 days

B) About 9 days

C) About 10 days

D) About 11 days

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:00, erykp17
Which statement is true? the given sides and angles cannot be used to show similarity by either the sss or sas similarity theorems. the given sides and angles can be used to show similarity by the sss similarity theorem only. the given sides and angles can be used to show similarity by the sas similarity theorem only. the given sides and angles can be used to show similarity by both the sss and sas similarity theorems.
Answers: 1
image
Mathematics, 21.06.2019 17:30, outlaw93
If you apply the below transformations to the square root parent function, f(x) = vx, what is the equation of the new function? • shift 12 units right. • shift seven units down.
Answers: 1
image
Mathematics, 21.06.2019 17:30, josh3419
Adriver from the university of florida women’s swimming and diving team is competing in the in ncaa zone b championships
Answers: 3
image
Mathematics, 21.06.2019 18:30, Angelanova69134
Someone answer this asap rn for ! a discount store’s prices are 25% lower than department store prices. the function c(x) = 0.75x can be used to determine the cost c, in dollars, of an item, where x is the department store price, in dollars. if the item has not sold in one month, the discount store takes an additional 20% off the discounted price and an additional $5 off the total purchase. the function d(y) = 0.80y - 5 can be used to find d, the cost, in dollars, of an item that has not been sold for a month, where y is the discount store price, in dollars. create a function d(c(x)) that represents the final price of an item when a costumer buys an item that has been in the discount store for a month. d(c(x)) =
Answers: 1
Do you know the correct answer?
An activity has a pessimistic time that is four times as long as its most likely time and six times...

Questions in other subjects:

Konu
History, 22.01.2020 10:31