When building a house the number of dats required to build varied inversely with the number of workers. One house was built in 85 days by 5 workers. How many days would it take to build a similar house with 17 workers

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:00, demetriascott20
Write the point-slope form of the line passing through (2, -12) and parallel to y=3x.
Answers: 2
image
Mathematics, 21.06.2019 22:00, rwlockwood1
If my mom gets $13.05 an hour, and she works from 3: 30 to 10: 45 in the morning, how much money does my mom make?
Answers: 1
image
Mathematics, 21.06.2019 22:40, AbigailHaylei
What are the excluded values? m+5/mn+3m
Answers: 1
image
Mathematics, 22.06.2019 01:40, googoo4
Given: prst square pmkd is a square pr = a, pd = a find the area of pmct.
Answers: 3
Do you know the correct answer?
When building a house the number of dats required to build varied inversely with the number of worke...

Questions in other subjects:

Konu
Advanced Placement (AP), 22.11.2020 16:20
Konu
Advanced Placement (AP), 22.11.2020 16:20
Konu
Mathematics, 22.11.2020 16:30