Mathematics
Mathematics, 04.04.2020 04:27, WhiteWinterRose

A particular project network has two paths through it: Path A and Path B. Path A has an expected completion time of 15 weeks and a variance in completion time of 8 weeks, while Path B has an expected completion time of 16 weeks and a variance in completion time of 4 weeks. What is the probability that this project is going to take more than 18 weeks?

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, keasiabrown25
Determine the difference: 3.2 × 1010 – 1.1 × 1010. write your answer in scientific notation.
Answers: 1
image
Mathematics, 21.06.2019 20:00, Luena
Which of the following is not a subset of {1,2,3}?
Answers: 2
image
Mathematics, 21.06.2019 23:00, lejeanjamespete1
Graph the system of equations. {6x−4y=−244x−8y=−32 use the line tool to graph the lines.
Answers: 1
image
Mathematics, 21.06.2019 23:30, adriandehoyos1p3hpwc
Write the percent as a fraction or mixed number in simplest form. 0.8%
Answers: 2
Do you know the correct answer?
A particular project network has two paths through it: Path A and Path B. Path A has an expected com...

Questions in other subjects:

Konu
Mathematics, 20.05.2020 19:01