2. Use the given process data to construct a control chart for p.
If the weight of cereal in a particular packet is less than 14 ounces, the packet is considered
nonconforming. Each week, the manufacturer randomly selects 1,000 cereal packets and determines
the number that are nonconforming. The results for 12 consecutive weeks are shown below.
46 32 21 30 47 31 32 52 48 45 62 58
Select the correct upper control limit.
OUCL = 0.0627
O UCL = 0.0610
O UCL = 0.0750
UCL = 0.0575

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:00, devontemiles1174
Will give brainliest if you answer question correct
Answers: 2
image
Mathematics, 21.06.2019 16:00, brandondees25
Afurniture manufacturer produces chairs and sofas. each chair requires 10 yards of fabric, and each sofa requires 20 yards of fabric. the manufacturer has 300 yards of fabric available. to fulfill orders, the number of sofas must be at least twice the number of chairs. let x be the number of chairs and y the number of sofas. which inequalities are described in the problem? check all of the boxes that apply
Answers: 2
image
Mathematics, 21.06.2019 19:30, kayli53531
Arestaurant charges $100 to rent its banquet room for an event. it also charges $15 to serve dinner to each guest. write an equation for the total cost of the banquet room in terms of the number of guests. deine your variables. what is the total cost of the banquet room for 20 guests?
Answers: 1
image
Mathematics, 21.06.2019 20:00, Ap621765
In one day there are too high tides into low tides and equally spaced intervals the high tide is observed to be 6 feet above the average sea level after six hours passed a low tide occurs at 6 feet below the average sea level in this task you will model this occurrence using a trigonometric function by using x as a measurement of time assume the first high tide occurs at x=0. a. what are the independent and dependent variables? b. determine these key features of the function that models the tide: 1.amplitude 2.period 3.frequency 4.midline 5.vertical shift 6.phase shift c. create a trigonometric function that models the ocean tide for a period of 12 hours. d. what is the height of the tide after 93 hours?
Answers: 1
Do you know the correct answer?
2. Use the given process data to construct a control chart for p.
If the weight of cereal in a...

Questions in other subjects:

Konu
Mathematics, 13.01.2021 19:00