Mathematics
Mathematics, 13.03.2020 18:20, cecem58

Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days. The probability that the project will be completed within 185 work-days is

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, jweldene12
Why do interests rates on loans to be lower in a weak economy than in a strong one
Answers: 2
image
Mathematics, 21.06.2019 18:30, jamalnellum56
The square pyramid has a volume of 441 cubic inches. what is the value of x? 1/7x is the height x is the base
Answers: 2
image
Mathematics, 21.06.2019 19:30, BarcaOsama
Which of the following is the explicit rule for a geometric sequence defined a recursive formula of a -5a for which the first term is 23?
Answers: 1
image
Mathematics, 21.06.2019 19:30, allicat133
Awater holding tank measures 105 m long, 50 m wide, and 8 m deep. traces of mercury have been found in the tank, with a concen- tration of 60 mg/l. what is the total mass of mercury in the tank? answer in units of kg.
Answers: 1
Do you know the correct answer?
Completion time (from start to finish) of a building remodeling project is normally distributed with...

Questions in other subjects:

Konu
Mathematics, 16.08.2021 21:30
Konu
Mathematics, 16.08.2021 21:30
Konu
Social Studies, 16.08.2021 21:30