A furniture company has four product types; Product1, Product2, Product3, and Product4. Four departments; A, B, C, and D are needed for producing these products. However, each product needs different steps to produce.

• Product1;
o Production Quantity (per day) = 5
o Routing: A-B-C-D-A
o Weight (movement factor) = 1
• Product2;
o Production Quantity (per day) = 10
o Routing: B-A-D
o Weight (movement factor) = 0.75
• Product3;
o Production Quantity (per day) = 15
o Routing: C-A-B-D
o Weight (movement factor) = 0.5
• Product4;
o Production Quantity (per day) = 20
o Routing: A-B-A-B
o Weight (movement factor) = 0.25

1) Develop a From-to chart.
2) Develop three-block layouts using the SLP. Assume that the total available space is 100*100 and the required spaces for the departments are 1000 (A), 2000 (B), 2000 (C), and 5000 (D).
3) Compute the distance-based objective values for the three layouts.
4) Compute the adjacency-based objective values for the three layouts.

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:30, alexanderavrett
Find the vertex of the function given below y=x^2-6x+1
Answers: 2
image
Mathematics, 22.06.2019 02:20, gungamer720
What is the length of ac in the given triangle?
Answers: 1
image
Mathematics, 22.06.2019 04:30, isabelperez063
Lucinda leaves money in her savings account for 8 years. she started with $800 and earned 3.5% interest compound annually. how much money is in her account?
Answers: 1
image
Mathematics, 22.06.2019 06:00, dad46
What is the equation of the line that passes through (3,5) and is parallel to y=2x+6
Answers: 2
Do you know the correct answer?
A furniture company has four product types; Product1, Product2, Product3, and Product4. Four departm...

Questions in other subjects:

Konu
Advanced Placement (AP), 30.07.2019 19:30