You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. The probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy)

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:00, raularriaga
You have 138.72 in your saving account u take out 45.23 and 18.00 you deposit 75.85 into your account
Answers: 1
image
Mathematics, 21.06.2019 20:00, angelthompson2018
Given: ∆mop p∆mop =12+4 3 m∠p = 90°, m∠m = 60° find: mp, mo
Answers: 1
image
Mathematics, 21.06.2019 21:10, samtrevino9921
Which exponential function has an initial value of 2? f(x) = 2(3x) f(x) = 3(2x)
Answers: 1
image
Mathematics, 21.06.2019 21:50, edjiejwi
Aline passes through the point (–7, 5) and has a slope of 1/2 which is another point that the line passes through?
Answers: 3
Do you know the correct answer?
You have just used the network planning model and found the critical path length is 30 days and the...

Questions in other subjects:

Konu
Mathematics, 28.08.2020 23:01
Konu
Mathematics, 28.08.2020 23:01
Konu
Biology, 28.08.2020 23:01
Konu
Mathematics, 28.08.2020 23:01