An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.

a) What are the minimum and maximum cycle times?
b) What range of output is theoretically possible for the line?
c) What is the minimum number of worksheets needed if the maximum output rate is to be sought?
d) What cycle time will provide an output rate of 125 units per day?
e) What output potential will result if the cycle time is (1) 9 minutes? and (2) 15 minutes?

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:30, Destiny8372
Complete the standard form of the equation that represents the quadratic relationship displayed above, where a, b, and c are rational numbers.
Answers: 1
image
Mathematics, 21.06.2019 17:00, softball2895
The center of a circle represent by the equation (x+9)^2+(y-6)^2=10^2 (-9,6), (-6,9), (6,-9) ,(9,-6)
Answers: 1
image
Mathematics, 21.06.2019 18:00, ReeseMoffitt8032
In a graph with several intervals o data how does a constant interval appear? what type of scenario produces a constant interval?
Answers: 1
image
Mathematics, 21.06.2019 19:00, hanahspeers
If f(x)= sqrt4x+9+2, which inequality can be used to find the domain of f(x)?
Answers: 2
Do you know the correct answer?
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total tim...

Questions in other subjects:

Konu
Mathematics, 05.02.2020 03:43