A bicycle manufacturing company makes a particular type of bike. Each child bike requires 4 hours to build and 4 hours to test. Each adult bike requires 6
hours to build and 4 hours to test. With the number of workers, the company is able to have up to 120 hours of building time and 100 hours of testing time for
a week. If crepresents child bikes and a represents adult bikes, determine which system of inequality best explains whether the company can build 10 child
bikes and 12 adult bikes in the week
Your
No, because the bike order does not meet the restrictions of 40 + 6a s 120 and 40 + 4a s 100
No, because the bike order does not meet the restrictions of 40 + 4a s 120 and 6C + 4a s 100
Yes, because the bike onder meets the restrictions of 40 + 6a s 120 and 40 + 4a s 100
Yes, because the bike order meets the restrictions of 4c + 4a s 120 and 6c + 4a s 100
lear answer
Pause test
Complete test
Back

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, huntbuck14
What is the range for 31,39,29,34,37,24,36,33,34,28
Answers: 1
image
Mathematics, 21.06.2019 18:40, helpme6191
(mc 02.03) what set of reflections and rotations would carry rectangle abcd onto itself? reflect over the y-axis, reflect over the x-axis, rotate 180° rotate 180°, reflect over the x-axis, reflect over the line y=x reflect over the x-axis, rotate 180°, reflect over the x-axis rotate 180, reflect over the y-axis, reflect over the line y=x
Answers: 1
image
Mathematics, 21.06.2019 23:00, Mypasswordishotdog11
John has 1/2 pound of oranges to share with julie. if they share the oranges equally, how much will each of them have?
Answers: 1
image
Mathematics, 22.06.2019 01:40, twinchristiansp4xhd2
Which of the following is the major negative aspect of crossover designs for research studies? a. prohibitive cost b. residual effects c-subject drepout d. incomplete randomization e. large sample size required
Answers: 1
Do you know the correct answer?
A bicycle manufacturing company makes a particular type of bike. Each child bike requires 4 hours to...

Questions in other subjects:

Konu
Mathematics, 06.03.2020 19:17
Konu
Mathematics, 06.03.2020 19:17