Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a 0.90 probability that the project will be completed before approximately day .
i.98
ii.108
iii.109
iv.115
v.118

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:30, ttglilrob
    choose the correct definition for  extremo.  a.  end      b.  extra      c.  extract      d.  eventual 
Answers: 2
image
Mathematics, 21.06.2019 23:00, sandyrose3012
Multiplying fractions by whole number 5 x 1/3=?
Answers: 2
image
Mathematics, 22.06.2019 01:20, love0000
Describe how to determine the average rate of change between x = 4 and x = 6 for the function f(x) = 2x^3 + 4. include the average rate of change in your answer.
Answers: 3
image
Mathematics, 22.06.2019 06:00, elirosejohlandancel
The question is on the attached picture, for those who .
Answers: 1
Do you know the correct answer?
Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a vari...

Questions in other subjects:

Konu
Social Studies, 26.11.2021 04:50
Konu
History, 26.11.2021 04:50