The time, t, required to complete a job
varies inversely with the number of people,
p, w...
Mathematics, 25.02.2020 23:15, ziaa9690
The time, t, required to complete a job
varies inversely with the number of people,
p, working on the job. If it takes 7.125
hours for 8 workers to complete a job, how
many hours will it take if there are 3
workers?