Which of the following statements regarding PERT analysis is NOT true? Only critical activities contribute to the project variance. Project standard deviation is the sum of all critical activity standard deviations. The most likely time is different from the expected activity time. Each activity has three estimates of its duration. Project variance is the sum of all critical activity variances.
Answers: 3
Mathematics, 21.06.2019 22:30, kdtd3163
In a certain city, the hourly wage of workers on temporary employment contracts is normally distributed. the mean is $15 and the standard deviation is $3. what percentage of temporary workers earn less than $12 per hour? a. 6% b. 16% c. 26% d. 36%
Answers: 1
Mathematics, 22.06.2019 01:00, Mypasswordishotdog11
Quadrilateral abcd is translated up and to the right, and then rotated about point q. which congruency statement is correct?
Answers: 1
Which of the following statements regarding PERT analysis is NOT true? Only critical activities cont...
Mathematics, 18.02.2020 21:38
Chemistry, 18.02.2020 21:39
Biology, 18.02.2020 21:39
Mathematics, 18.02.2020 21:39
Biology, 18.02.2020 21:39