Mathematics, 21.02.2020 20:53, slaybyely

Five data entry operators work at the data processing department of the Birmingham Bank. Each day for 30 days, the number of defective records in a sample of 300 records typed by these operators has been noted, as follows:

Sample No.

No. Defectives

Sample No.

No. Defectives

Sample No.

No. Defectives

1

8

11

7

21

17

2

4

12

5

22

13

3

19

13

16

23

6

4

10

14

3

24

6

5

12

15

12

25

13

6

9

16

8

26

11

7

11

17

13

27

15

8

10

18

4

28

7

9

6

19

18

29

13

10

14

20

17

30

4

a) Establish 3σ upper and lower control limits.

UCLp = (enter your response as a number between 0 and 1, rounded to three decimal places).

LCPp =(enter your response as a number between 0 and 1, rounded to three decimal places).

b) Why can the lower limit not be a negative number? (I actually know this one but I wanna get all the points down)

c) The industry standards for the upper and lower control limits are 0.10 and 0.01, respectively. What does this imply about Birmingham Bank's own standards?

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 12:30, edna27
(note i put the graph in so plz )the graph shows the amount of water that remains in a barrel after it begins to leak. the variable x represents the number of days that have passed since the barrel was filled, and y represents the number of gallons of water that remain in the barrel. what is the slope of the line
Answers: 1
image
Mathematics, 21.06.2019 20:20, leximae2186
Consider the following estimates from the early 2010s of shares of income to each group. country poorest 40% next 30% richest 30% bolivia 10 25 65 chile 10 20 70 uruguay 20 30 50 1.) using the 4-point curved line drawing tool, plot the lorenz curve for bolivia. properly label your curve. 2.) using the 4-point curved line drawing tool, plot the lorenz curve for uruguay. properly label your curve.
Answers: 2
image
Mathematics, 22.06.2019 00:00, bri9263
(20 points) a bank has been receiving complaints from real estate agents that their customers have been waiting too long for mortgage confirmations. the bank prides itself on its mortgage application process and decides to investigate the claims. the bank manager takes a random sample of 20 customers whose mortgage applications have been processed in the last 6 months and finds the following wait times (in days): 5, 7, 22, 4, 12, 9, 9, 14, 3, 6, 5, 15, 10, 17, 12, 10, 9, 4, 10, 13 assume that the random variable x measures the number of days a customer waits for mortgage processing at this bank, and assume that x is normally distributed. 2a. find the sample mean of this data (x ě…). 2b. find the sample variance of x. find the variance of x ě…. for (c), (d), and (e), use the appropriate t-distribution 2c. find the 90% confidence interval for the population mean (îľ). 2d. test the hypothesis that îľ is equal to 7 at the 95% confidence level. (should you do a one-tailed or two-tailed test here? ) 2e. what is the approximate p-value of this hypothesis?
Answers: 2
image
Mathematics, 22.06.2019 00:30, lolagrace06
Me i’m stuck on all these questions besides the two bottom ones
Answers: 2