Suppose a particular project has an expected completion time of 30 days; in other words, the critical path takes 30 days to finish. Further, the variance of the critical path is 25. Based on this information, please answer the following questions:

Find the probability that the project:
(1) Would be completed within 40 days
(2) Would take longer than 40 days to finish
(3) Would be completed within 20 days
(4) Would take longer than 20 days to finish

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:30, MayFlowers
This is about circle theorems. someone asap : (
Answers: 1
image
Mathematics, 22.06.2019 00:20, lreese
Convert the number to decimal form. 12) 312five a) 82 b) 30 c) 410 d) 1560 13) 156eight a) 880 b) 96 c) 164 d) 110 14) 6715eight a) 53,720 b) 3533 c) 117 d) 152
Answers: 1
image
Mathematics, 22.06.2019 02:10, toxsicity
Susan is paying $0.30 per $100 on her $483,000 home in homeowners insurance annually. if her annual homeowners insurance premium is divided into twelve equal monthly installments to be included on each of her monthly mortgage payments of $2,128.00, what is her total monthly payment?
Answers: 2
image
Mathematics, 22.06.2019 02:30, dchirunga23
How many degrees are there in the central angles in a circle
Answers: 1
Do you know the correct answer?
Suppose a particular project has an expected completion time of 30 days; in other words, the critica...

Questions in other subjects: