Suppose a particular project has an expected completion time of 30 days; in other words, the critical path takes 30 days to finish. Further, the variance of the critical path is 25. Based on this information, please answer the following questions:
Find the probability that the project:
(1) Would be completed within 40 days
(2) Would take longer than 40 days to finish
(3) Would be completed within 20 days
(4) Would take longer than 20 days to finish
Answers: 1
Mathematics, 22.06.2019 02:10, toxsicity
Susan is paying $0.30 per $100 on her $483,000 home in homeowners insurance annually. if her annual homeowners insurance premium is divided into twelve equal monthly installments to be included on each of her monthly mortgage payments of $2,128.00, what is her total monthly payment?
Answers: 2
Mathematics, 22.06.2019 02:30, dchirunga23
How many degrees are there in the central angles in a circle
Answers: 1
Suppose a particular project has an expected completion time of 30 days; in other words, the critica...
Mathematics, 27.08.2019 02:10
Computers and Technology, 27.08.2019 02:10
Computers and Technology, 27.08.2019 02:10