A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. What is the probability that the project can be completed between days 108 and 120?A) 0.0227B) 0.1058C) minus−2.00D) 0.9773E) 0.4773

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 23:00, grettelyesenia
Find the dimensions of the circle. area = 64π in.² r= in.
Answers: 1
image
Mathematics, 21.06.2019 23:30, pr4ever
Petes dog weighed 30 pounds it then lost 16% of it's weight how much did pete lose
Answers: 2
image
Mathematics, 22.06.2019 00:30, myla18jabbar
Each day jake donates money to the global.
Answers: 1
image
Mathematics, 22.06.2019 00:30, jjjones2233
The mean average cost of standard room per night at a hostel is ? 20.60. therefore, how much does a standard room cost per night at night-time rest days?
Answers: 1
Do you know the correct answer?
A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the c...

Questions in other subjects: