Agroup of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hours. however, after working 8 hours, some of the workers left the group and the remaining workers could complete the job in 72 hours. how many workers left the team?

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:30, uchapman6286
What is the lcm of 16 and 40 ? 24 and 40 ?
Answers: 2
image
Mathematics, 21.06.2019 21:30, Buttercream16
Jude is making cement for a driveway. the instructions show the amount of each ingredient to make 1 batch of cement. complete each statement to adjust the ingredients for each new situation if jude uses these instructions.
Answers: 3
image
Mathematics, 21.06.2019 22:10, karinagramirezp072gb
2. using calculations based on a perpetual inventory system, determine the inventory balance altira would report in its august 31, 2021, balance sheet and the cost of goods sold it would report in its august 2021 income statement using the average cost method. (round "average cost per unit" to 2 decimal places.)
Answers: 1
image
Mathematics, 21.06.2019 22:10, andy6128
Rationalize the denominator- 12x/√x-10
Answers: 1
Do you know the correct answer?
Agroup of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hours...

Questions in other subjects:

Konu
Biology, 13.06.2020 01:57