Aconstruction company has 8 identical jobs. with everyone working the same rate, it takes 8 workers 6 days to complete 3 identical jobs. if 3 of the workers leave and each of the workers maintain their work pace, how long will it take the remaining 5 workers to complete the remaining jobs?

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 13:50, daytonalive7193
Asimple random sample of size nequals14 is drawn from a population that is normally distributed. the sample mean is found to be x overbar equals 70 and the sample standard deviation is found to be sequals13. construct a 90% confidence interval about the population mean
Answers: 2
image
Mathematics, 21.06.2019 17:30, Zeniko
Asailor is looking at a kite. if he is looking at the kite at an angle of elevation of 36and the distance from the boat to the point where the kite is directly overhead is 40 feet, how high is the kite?
Answers: 1
image
Mathematics, 21.06.2019 23:00, arnold2619
How many 3-digit numbers can you write using only digits 1 and 7? (of course, digits can repeat.) how many 3-digit numbers can you write using only digits 1 and 7? (of course, digits can repeat.)
Answers: 2
image
Mathematics, 22.06.2019 01:30, karsenbeau
Given are five observations for two variables, x and y. xi 1 2 3 4 5 yi 3 7 5 11 14 which of the following is a scatter diagrams accurately represents the data? what does the scatter diagram developed in part (a) indicate about the relationship between the two variables? try to approximate the relationship betwen x and y by drawing a straight line through the data. which of the following is a scatter diagrams accurately represents the data? develop the estimated regression equation by computing the values of b 0 and b 1 using equations (14.6) and (14.7) (to 1 decimal). = + x use the estimated regression equation to predict the value of y when x = 4 (to 1 decimal). =
Answers: 3
Do you know the correct answer?
Aconstruction company has 8 identical jobs. with everyone working the same rate, it takes 8 workers...

Questions in other subjects: