Xyz company uses "continuous review system (q, rop)" for an item. lead-time is currently one week. the average demand during the week is 100 units with a standard deviation of 20 units. if the supplier increases lead-time to 4 weeks, what will be the standard deviation of lead-time demand?
a.40 80
b.17.89
c.44.72
d.120

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:00, NicoleQuinn
Find the sum of the measure of the interior angles of a polygon of 9 sides ; of 32 sides
Answers: 1
image
Mathematics, 21.06.2019 21:00, vrentadrienneoqug1a
Ian is in training for a national hot dog eating contest on the 4th of july. on his first day of training, he eats 4 hot dogs. each day, he plans to eat 110% of the number of hot dogs he ate the previous day. write an explicit formula that could be used to find the number of hot dogs ian will eat on any particular day.
Answers: 3
image
Mathematics, 21.06.2019 21:30, ramirex9680
What is the volume of this container?
Answers: 2
image
Mathematics, 21.06.2019 23:30, brendacauani12345
Which of the following statements would be sufficient to prove that parallelograms pqrs is a rectangle ?
Answers: 2
Do you know the correct answer?
Xyz company uses "continuous review system (q, rop)" for an item. lead-time is currently one week. t...

Questions in other subjects:

Konu
History, 15.07.2019 17:10