Ou have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level, what should be that time (in days and round to the nearest whole number.)

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 12:30, elleinad5656
On the april 3 billing date, michaelle chappell had a balance due of $ 1495.39 on her credit card. from april 3 through may 2, michaelle charged an additional $ 305.34 and made a payment of $ 800.a) find the finance charge on may 3, using the previous balance method. assume that the interest rate is 1.8 % per month. b) find the new balance on may 3.
Answers: 2
image
Mathematics, 21.06.2019 19:30, Tcareyoliver
If 2(a^2+b^2)=(a+b)^2 then, > a+b=0, > ab=0, > a=b, > 2a=b
Answers: 1
image
Mathematics, 22.06.2019 00:00, jadfavors4321
Parallelogram efgh is a rectangle. he = 6, and fe = 8. find ge: and find fj:
Answers: 1
image
Mathematics, 22.06.2019 04:20, alcantar28eduin
Tanner has purchased a car with a loan. his bank now deducts the amount of the monthly payment from his account on the second of every month. which financial service has tanner’s bank offered him? a. money transfer b. automated payment c. online banking d. atm withdrawal
Answers: 2
Do you know the correct answer?
Ou have just used the network planning model for a county road resurfacing project and found the cri...

Questions in other subjects:

Konu
Mathematics, 03.10.2019 02:30
Konu
Mathematics, 03.10.2019 02:30
Konu
Mathematics, 03.10.2019 02:30