Aproduct has 2 sub-assemblies (sa1 and sa2). it requires 1 unit of sa1 and 2 units of sa2. it takes 2 days to assemble the product. subassembly 1 (sa1) has 3 components (c11, c12 and c13), and it takes 3 days to assemble sa1. it takes (1, 2, 1) days to fabricate c11, c12 and c13 respectively. subassembly 2 (sa2) has 3 components (c21, c22 and c23), and it takes 2 days to assemble sa2. it takes (3, 2, 2) days to fabricate c21, c22 and c23 respectively. a. fill in the bom table for the product with fields for component level, component id quantity and lead time. b. what is the minimum manufacturing lead time for the product. c. what are the differences between how a push planning system would handle demand for this product versus a pull system?
![answer](/tpl/images/cats/otvet.png)
Answers: 1
Other questions on the subject: Mathematics
![image](/tpl/images/cats/mat.png)
Mathematics, 21.06.2019 21:30, sassy11111515
Cal's go cart has a gas tank with the dimensions shown below. he uses a gas can that holds 11 gallon of gas, to fill the go cart tank. 11 gallon = 231 inches^3 how many full gas cans will it take to fill the go cart's gas tank?
Answers: 3
![image](/tpl/images/cats/mat.png)
![image](/tpl/images/cats/mat.png)
Do you know the correct answer?
Aproduct has 2 sub-assemblies (sa1 and sa2). it requires 1 unit of sa1 and 2 units of sa2. it takes...
Questions in other subjects:
![Konu](/tpl/images/cats/obshestvoznanie.png)
Social Studies, 07.01.2020 06:31
![Konu](/tpl/images/cats/mat.png)
Mathematics, 07.01.2020 06:31
![Konu](/tpl/images/cats/mat.png)
Mathematics, 07.01.2020 06:31
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/biologiya.png)
Biology, 07.01.2020 06:31
![Konu](/tpl/images/cats/mat.png)
Mathematics, 07.01.2020 06:31
![Konu](/tpl/images/cats/mat.png)
Mathematics, 07.01.2020 06:31
![Konu](/tpl/images/cats/en.png)
![Konu](/tpl/images/cats/informatica.png)
Computers and Technology, 07.01.2020 06:31