A six-station automatic assembly line has an ideal cycle time of 12 sec. Downtime occurs for two reasons. First, mechanical and electrical failures cause the line to stop that occur with a frequency of once per 50 cycles. The average downtime for these causes is 3 min. Second, defective components also result in downtime. The fraction defect rate for each of the six components added to the base parts at the six stations is 2%. The probability that a defective component will cause a station jam is 0.5 for all stations. Downtime per occurrence for defective parts is 2 min. Determine a) Yield of assemblies that are free of defective components? (5 marks)

b) proportion of assemblies that contain at least one defective component? (2 marks)

c) Average production rate of the good products? (10 marks)

d) Uptime efficiency? (3 marks)

answer
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 15:10, EmilySerna
Heat is added to a piston-cylinder device filled with 2 kg of air to raise its temperature 400 c from an initial temperature of t1 27 cand pressure of pi 1 mpa. the process is isobaric process. find a)-the final pressure p2 b)-the heat transfer to the air.
Answers: 1
image
Engineering, 03.07.2019 15:10, theamandawhite
Ahouse has the following electrical appliance usage (1) single 40w lamp used for 4 hours per day (2) single 60w fan used for 12 hours per day (3) single 200w refrigerator that runs 24 hours per day with compressor run 12 hours and off 12 hours find the solar power inverter size in watt with correction factor of 1.25.
Answers: 1
image
Engineering, 04.07.2019 12:10, Ryantimes2
On a average work day more than work place firs are reorted
Answers: 1
image
Engineering, 04.07.2019 18:10, caitlynnpatton1208
Water in a partially filled large tank is to be supplied to the roof top, which is 8 m above the water level in the tank, through a 2.2-cm-internal-diameter pipe by maintaining a constant air pressure of 300 kpa (gage) in the tank. if the head loss in the piping is 2 m of water, determine the discharge rate of the supply of water to the roof top in liters per second.
Answers: 3
Do you know the correct answer?
A six-station automatic assembly line has an ideal cycle time of 12 sec. Downtime occurs for two rea...

Questions in other subjects:

Konu
Mathematics, 27.01.2020 22:31