After receiving Notice to Proceed (assume a duration of zero), the Pipe Pro project engineers will begin processing submittals for the materials to the engineers. The submittals activity should take approximately 6 days, which will give adequate time for them to be returned from the engineering team. Right after the submittals are returned, the team will take a day to order material. For the bedding material, delivery will take 5 days. For the pipe, delivery will take 14 days. Also following NTP, mobilization can start and should take approximately 4 days. After mobilization is complete, excavation of the trench can begin and will take 5 days. Following excavation and bedding material delivery, the bedding material can be placed in the trench and this will take 3 days. Then the bedding material will be compacted and this will take 3 days. Once the trench is prepped with the bedding material, the pipe can begin being laid, after it has arrived on site. It will take approximately 9 days to complete the pipe laying activity. It will then take about 3 days for the trench to be backfilled. Next, the backfill material will be compacted and you should expect this to take 2 day. Site clean-up should take about 2 days. Lastly, the engineers will inspect the site. Anticipate the final inspections will take 2 days. Finally, the terminal activity will be demobilization and this will take at least 1 day. Based on the information regarding the activities’ relationships you must create a schedule for the construction of the storm water system. Use days as the duration unit for the schedule
a. Develop a list of necessary activities and their corresponding durations. Provide this list as an accompaniment for the provided table.
b. Create an Activity on the Node Network, based on the logical relationships of the activities. Include Start and Finish activities. Provide a diagram of this network with your memo.
c. For each activity, calculate the Early Start (ES), Late Start (LS), Early Finish (EF), and Late Finish (LF).

answer
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 15:10, brooklyn674
Apiston-cylinder with a volume of 0.25 m3 holds 1 kg of air (r 0.287 k/kgk) at a temperature of 100 c. heat transfer to the cylinder causes an isothermal expansion of the piston until the volume triples. how much heat is added to the piston-cylinder?
Answers: 3
image
Engineering, 04.07.2019 18:10, juansoto227711
Journeyman training is usually related (clo2) a)-to specific tasks b)-to cost analysis of maintenance task c)-to control process to ensure quality d)-to installation of machinery
Answers: 2
image
Engineering, 04.07.2019 18:20, aly95
An engine runs on the ideal diesel cycle. the cycle has a compression ratio of 20 and a cutoff ratio of 2. the highest temperature in the cycle is 1200 k. if the heat into the system is 300 kj/kg of working fluid and using variable specific heats determine the work produced per mass of working fluid
Answers: 3
image
Engineering, 04.07.2019 18:20, miguel454545
Along 8-cm diameter steam pipe whose external surface temperature is 900c connects two buildings. the pipe is exposed to ambient air at 70c with a wind speed of 50 km/hr blowing across the pipe. determine the heat loss from the pipe per unit length. (b) air at 500c enters a section of a rectangular duct (15 cm x 20 cm) at an average velocity of 7 m/s. if the walls of the duct are maintained at 100c. a) the length of the tube for an exit temperature of the air to be 40 0c. b)the rate of heat transfer from the air. c) the fan power needed to overcome the pressure drop in this section of the duct.
Answers: 1
Do you know the correct answer?
After receiving Notice to Proceed (assume a duration of zero), the Pipe Pro project engineers will b...

Questions in other subjects:

Konu
Mathematics, 01.07.2019 15:00