The agency CM is managing a contract that installs interior finish work for an underground pedestrian tunnel. The concrete tunnel shell was constructed under another contract over a year ago. The shell contract specified embeds in the cast-in-place ceiling for hanging all-thread to support chilled water pipes. The finishes contractor has discovered that only expansion anchors were installed, which will not support the pipe weight. He proposes a costly change to retrofit embeds using epoxy. The CM learns that the tunnel shell designer approved the shell contractor's submittal for the expansion anchors. Which of the following is the CM's best course of action? a. Contact the shell designer to design and contract for the repair based on the submittal approved in error.
b. Ask a third party task order contractor to design and install the retrofit with back charge to the shell contractor and shell designer in proportion to their contract dollar values.
e. Issue a change order to the finishes contractor for the epoxy embeds. Seek to recover from the designer or shell contractor.
d. Contact the shell contractor to do the retrofit based on a latent defect.

answer
Answers: 3

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 12:10, Ryantimes2
On a average work day more than work place firs are reorted
Answers: 1
image
Engineering, 04.07.2019 18:10, niicoleassssssf
Aflywheel accelerates for 5 seconds at 2 rad/s2 from a speed of 20 rpm. determine the total number of revolutions of the flywheel during the period of its acceleration. a.5.65 b.8.43 c. 723 d.6.86
Answers: 2
image
Engineering, 04.07.2019 18:10, alyssabailey7545
Give heat transfer applications for the following, (i) gas turbines (propulsion) ) gas turbines (power generation). (iii) steam turbines. (iv) combined heat and power (chp). (v) automotive engines
Answers: 1
image
Engineering, 04.07.2019 18:10, krystabrewer3
What are the two (02) benefits, which may result from a successful implementation of preventive maintenance (pm) program in an organization? (clo3)a)- lean manufacturing b)-overlapping responsibilities c)-the planner is not qualified d)-accurate contractor information e)-reduction in equipment redundancies f)-accurate stores information
Answers: 3
Do you know the correct answer?
The agency CM is managing a contract that installs interior finish work for an underground pedestria...