In a standard 6-day period, the production department programme a specific machine to work for 250 hours- its loading time. Changeovers and set-ups take average of 8 hours and breakdown failures average 3 hours every 6 days.
The time when the machine cannot work because it is waiting for material to be delivered from other parts of the process is 1 hour on average and during the period when the machine is running, it averages 92 per cent of its rated speed.
Two per cent of the parts processed by the machine are subsequently found to be defective in some way.

Based on above data, calculate overall equipment effectiveness (OEE)

answer
Answers: 1

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 14:10, cowgyrlup124
Explain the difference laminar and turbulent flow. explain it with the shear stress and the velocity profiles.
Answers: 1
image
Engineering, 04.07.2019 18:10, niicoleassssssf
Aflywheel accelerates for 5 seconds at 2 rad/s2 from a speed of 20 rpm. determine the total number of revolutions of the flywheel during the period of its acceleration. a.5.65 b.8.43 c. 723 d.6.86
Answers: 2
image
Engineering, 04.07.2019 18:10, michellerosas
Ajournal bearing has a journal diameter of 3.250 in with a unilateral tolerance of 20.003 in. the bushing bore has a diameter of 3.256 in and a unilateral tolerance of 0.004 in. the bushing is 2.8 in long and supports a 700-lbf load. the journal speed is 900 rev/min. find the minimum oil film thickness and the maximum film pressure for both sae 20 and sae 20w-30 lubricants, for the tightest assembly if the operating film temperature is 160°f. a computer code is appropriate for solving this problem.
Answers: 3
image
Engineering, 04.07.2019 19:10, Lexi5170
A)-explain briefly the importance of standards in engineering design. b)- what is patent? c)-explain the relationship between these standards: b. s. and b. s.en d)- in engineering design concepts, types of loads and how they act are important factors. explain.
Answers: 3
Do you know the correct answer?
In a standard 6-day period, the production department programme a specific machine to work for 250 h...

Questions in other subjects:

Konu
Mathematics, 28.11.2019 23:31