A contractor excavates 10,000 m3 soil at moist unit weight of 17.5 kN/m3 and moisture content of 10% from a borrow pit and transports it to a project site. The project has an area of 20,000 m2 to be filled with this compacted soil. If the required dry unit weight and moisture content of the compacted soil are 18.3 kN/m3 and 12.5% (assume there is no soil loss during transportation and compaction), what is the thickness of the compacted soil and how much water needs to be added?

answer
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:20, Doogsterr
For each of the following process: a) sketch the p-v diagram, b)sketch t-s diagram, c) sketch t-v diagram, d) sketch the boundary work on one of the diagrams (a, b or c) and e) sketch the reversible heat transfer on one of the diagrams (a, b or c): 1- isobaric process from compressed liquid to superheated vapor 2- isothermal process from compressed liquid to superheated vapor 3- isentropic process from compressed liquid to superheated vapor
Answers: 3
image
Engineering, 04.07.2019 19:10, pjgolden04
How to increase the thermal officiency of an ideal simple rankino cycle? among these methods, which one is the best and why?
Answers: 2
image
Engineering, 04.07.2019 19:20, holaadios222lol
Apiping systems consists of 6 m of 6-std type k and 12 m of 4-std type k, both drawn copper tubing. the system conveys ethylene glycol at a rate of 0.013 m3/s. the pressure drop across the system is to be calculated. there are two 90° elbows in the 6-in pipe, a reduction from the 6-in pipe to the 4-in pipe and four 90° elbows in the 4-in pipe. all fittings are soldered (same as flanged) and regular. the inlet and outlet of the system are at the same height.
Answers: 1
image
Engineering, 05.07.2019 19:10, justin20080
Tech a says never use a water hose to clean up dust after a repair. tech b says never use a floor scrubber to clean up dust after repairs. who is correct?
Answers: 1
Do you know the correct answer?
A contractor excavates 10,000 m3 soil at moist unit weight of 17.5 kN/m3 and moisture content of 10%...

Questions in other subjects:

Konu
English, 11.09.2020 09:01
Konu
Mathematics, 11.09.2020 09:01
Konu
Mathematics, 11.09.2020 09:01
Konu
English, 11.09.2020 09:01
Konu
Mathematics, 11.09.2020 09:01
Konu
Mathematics, 11.09.2020 09:01
Konu
Mathematics, 11.09.2020 09:01
Konu
Mathematics, 11.09.2020 09:01
Konu
English, 11.09.2020 09:01
Konu
Mathematics, 11.09.2020 09:01