Engineering, 19.02.2021 03:00, weeman7760

There are three 15 LCY trucks that will be used to transport the excavated soil. It takes 25 min for a truck to drive to the unloading site, unload and drive back to the excavation area. Instead of being idle till the trucks return from each truck cycle, the excavator unloads soil in a spoil bank at the same swing angle (90o). Calculate the volume of soil in the spoil bank at the end of the excavation. Total volume of excavation is 15,000 BCY.

answer
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, yasminothman02
An air conditioning system consist of a 5 cm diameter pipe, operating at a pressure of 200 kpa. the air initially enters the pipe at 15°c with a velocity of 20 m/s and relative humidity of 80%. if the heat supply throughout the process is 960 w, determine the relative humidity and the temperature at the outlet
Answers: 3
image
Engineering, 04.07.2019 18:10, lillygrl100
For the closed feedwater heater below, feedwater enters state 3 at a pressure of 2000 psia and temperature of 420 °f at a rate of ix10 ibhr. the feedwat extracted steam enters state 1 at a pressure of 1000 psia and enthalpy of 1500 btu/lbm. the extracted er leaves at an enthalpy of 528.7 btu/lbm steam leaves as a saturated liquid. (16) a) determine the mass flow rate of the extraction steam used to heat the feedwater (10) b) determine the terminal temperature difference of the closed feedwater heater
Answers: 3
image
Engineering, 04.07.2019 18:10, xboxdude06
Slip occurs via two partial dislocations because of (a) the shorter path of the partial dislocation lines; (b) the lower energy state through partial dislocations; (c) the charge balance.
Answers: 1
image
Engineering, 04.07.2019 18:10, mirmir62
Machinery that is a key part of the process and without which the plant or process cannot function is classifed as: (clo4) a)-critical machinery b)-essential machinery c)-general purpose machinery d)-none of the specified options.
Answers: 1
Do you know the correct answer?
There are three 15 LCY trucks that will be used to transport the excavated soil. It takes 25 min for...

Questions in other subjects: