Engineering, 04.07.2020 02:01, mimithurmond03

Compare three alternatives on the basis of their capitalized costs at i = 10% per year. Alternative E F G
First cost, $ −50,000 −300,000 −900,000
AOC, $ per year −30,000 −10,000 −3,000
Salvage value, $5,000 70,000 200,000
Life, years 2 4 [infinity]

Note that the LCM of 2, 4 and [infinity] is [infinity]

answer
Answers: 3

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, ahmedeldyame
Aloaded platform of total mass 500 kg is supported by a dashpot and by a set of springs of effective stiffness 72 kn/m. it is observed that when the platform is depressed through a distance x = 12.5 cm below its equilibrium position and then released without any initial velocity; it reaches its equilibrium position in the shortest possible time without overshoot. find the position and velocity of the loaded platform 0.10 sec. after its release. if a further load of 400 kg is added to the platform, find, i) the frequency of damped vibrations, and i) the amplitude of vibration after 2 complete oscillations, given that the initial amplitude is 15 cm.
Answers: 1
image
Engineering, 04.07.2019 18:10, yasminothman02
An air conditioning system consist of a 5 cm diameter pipe, operating at a pressure of 200 kpa. the air initially enters the pipe at 15°c with a velocity of 20 m/s and relative humidity of 80%. if the heat supply throughout the process is 960 w, determine the relative humidity and the temperature at the outlet
Answers: 3
image
Engineering, 04.07.2019 18:20, mjcbs21
What is the heat treatment of metals? what is the benefit of it? why and how it's useful? answer in details, do not write by hand.
Answers: 3
image
Engineering, 04.07.2019 18:20, rocio5649
Amixture of slurry and mud is to be pumped through a horizontal pipe of diameter 500 mm. the fluid behaves as a bingham plastic with a yield stress of 30 pa and viscosity 0.04 pa. s. describe the effects of the shear stress through a transverse section of the pipe by plotting the variation in shear stress and velocity profile: (i) just before the slurry starts to move (ii) as the slurry flows when the pressure gradient is double that in part (i)
Answers: 3
Do you know the correct answer?
Compare three alternatives on the basis of their capitalized costs at i = 10% per year. Alternative...

Questions in other subjects: