A heavy construction firm has been awarded a contract to build a large concrete dam. It is expected that a total of 8 years will be required to complete the work. The firm will buy $600,000 worth of special equipment for the job. During the preparation of the job cost estimate, the following utilization schedule was computed for the special equipment: Year Utilization (hr/yr)
1 6000
2 4000
3 4000
4 1600
5 800
6 800
7 2200
8 2200
At the end of the job, it is estimated that the equipment can be sold at auction for $60,000.
(a) Compute the sum-of-years-digits' depreciation schedule.
(b) Compute the unit-of-production depreciation schedule

answer
Answers: 3

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:20, moneywaydaedae
Air is compressed isentropically from an initial state of 300 k and 101 kpa to a final temperature of 1000 k. determine the final pressure using the following approaches: (a) approximate analysis (using properties at the average temperature) (b) exact analysis
Answers: 1
image
Engineering, 04.07.2019 19:10, kimmy6973
What is creep? what is stress relaxation?
Answers: 1
image
Engineering, 06.07.2019 03:10, DeathFightervx
Air is flows through an adiabatic nozzle with an inlet pressure of 400 psia at a temperature of 300°f and a velocity of 20 ft/s. the outlet pressure is 40 psia and the velocity is 800 ftl/s. determine the outlet temperature of the air using: a) property tables b) specific heat (using the specific heat value for air at 300°f)
Answers: 3
image
Engineering, 06.07.2019 03:20, mardell2587
Acountershaft is supported by two tapered roller bearings using indirect mounting. the radial bearing loads are 1120 lb for the left-hand bearing and 2190 lb for the right-hand bearing. the shaft rotates at 400 rpm and is to have an l10 life of 40,000 hours and an application factor of 1.4. assume ka2k 15, and find the required radial rating of each bearing
Answers: 3
Do you know the correct answer?
A heavy construction firm has been awarded a contract to build a large concrete dam. It is expected...

Questions in other subjects:

Konu
Mathematics, 27.10.2020 16:50