Engineering, 19.03.2020 04:51, SketchWasTaken

A truck with heaped capacity of 10 cy is used to disposed to excavated material at dumpsite of 5 miles from the job site. The average velocity of the is 30 mph. The dump time is 30 second and load time is 50 second. Determine the production capacity of the dump truck.

answer
Answers: 1

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 14:10, volleyballfun24
If the thermal strain developed in polyimide film during deposition is given as 0.0044. assume room temperature is kept at 17.3 c, and thermal coefficient of expansion for the film and the substrate are 54 x 10^-6c^-1 and 3.3 x 10^-6c^-1respectively. calculate the deposition temperature.
Answers: 3
image
Engineering, 04.07.2019 18:10, mm016281
What difference(s) did you notice using a pneumatic circuit over hydraulic circuit. explain why the pneumatic piston stumbles when it hits an obstacle.
Answers: 2
image
Engineering, 04.07.2019 18:10, oliviasoreo92
Compute the pressure drop of 30°c air flowing with a mean velocity of 8 m/s in a circular sheet-metal duct 300 mm in diameter and 15 m long. use a friction factor, f 0.02, and pair = 1.1644 kg/m a. 37.26 pa b. 25.27 pa n c. 29.34 pa d. 30.52 pa
Answers: 1
image
Engineering, 04.07.2019 19:10, jennymares
Abarometer contains mercury with a density of 13600 kg/m3. atmospheric conditions are 95.8 kpa and 20 °c at 20 °c, the vapor pressure of the mercury is 0.000173 kpa. the column of mercury will rise to a height of most nearly. select one: a)- 0.38 m b)- 0.82 m c)- 0.48 m d)- 0.72 m
Answers: 1
Do you know the correct answer?
A truck with heaped capacity of 10 cy is used to disposed to excavated material at dumpsite of 5 mil...

Questions in other subjects:

Konu
Mathematics, 18.03.2020 04:21
Konu
Mathematics, 18.03.2020 04:21
Konu
Mathematics, 18.03.2020 04:21