Engineering, 14.02.2020 04:09, noahdavis58

During a particular 40-hour week of an automated production operation, 381 acceptable (nondefective) parts and 17 defective parts were produced. The operation cycle consists of a processing time of 5.23 min, and a part handling time of 0.58 min. Every 50 parts, a tool change is performed, and this takes 4.2 min. The machine experienced several breakdowns during the week.
Determine
(a) hourly production rate of acceptable parts,
(b) scrap rate, and
(c) availability (proportion uptime) of the machine during this week.

answer
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 14:10, bryneosburn
Line joining liquid phase with liquid and solid phase mixture is known as: a) liquidus b) solidus c) tie line d) none of the mentioned
Answers: 2
image
Engineering, 04.07.2019 18:20, samantha636
Avolume of 2.65 m3 of air in a rigid, insulated container fitted with a paddle wheel is initially at 264 k, 5.6 bar. the air receives 432 kj by work from the paddle wheel. assuming the ideal gas model with cv = 0.71 kj/kg • k, determine for the air the amount of entropy produced, in kj/k
Answers: 2
image
Engineering, 04.07.2019 18:20, 21megoplin
How much power could a wind turbine produce if it had the following specifications? cp = 0.45 -d=1.2kg/m3 d=50m v 5m/s
Answers: 2
image
Engineering, 04.07.2019 19:10, pjgolden04
How to increase the thermal officiency of an ideal simple rankino cycle? among these methods, which one is the best and why?
Answers: 2
Do you know the correct answer?
During a particular 40-hour week of an automated production operation, 381 acceptable (nondefective)...

Questions in other subjects:

Konu
Mathematics, 28.04.2021 05:30
Konu
Mathematics, 28.04.2021 05:30
Konu
Computers and Technology, 28.04.2021 05:30
Konu
Mathematics, 28.04.2021 05:30