Engineering, 20.12.2019 05:31, tatirocks1870

A120 cy per hr maximum output pump is used to place the concrete for a 200 cy slab. the concrete is supplied by 8 cytransit-mix trucks arriving to the site on 12 min intervals. the concrete batch plant is located 5 miles from the site. averagetruck speed is 30 mph. each transit-mix truck takes, on average, 10 min to discharge. the placement crew size is 7 workers. average worker output is 5 cy of concrete per hr. (a) how long will the operation take? (b) how can the operation bereorganized more effectively?

answer
Answers: 3

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 19:30, 10040813
When using the ohmmeter function of a digital multimeter, the leads are placed in what position relative to the component being tested? a. parallel b. control c. series d. line
Answers: 3
image
Engineering, 04.07.2019 18:10, ahmedeldyame
Aloaded platform of total mass 500 kg is supported by a dashpot and by a set of springs of effective stiffness 72 kn/m. it is observed that when the platform is depressed through a distance x = 12.5 cm below its equilibrium position and then released without any initial velocity; it reaches its equilibrium position in the shortest possible time without overshoot. find the position and velocity of the loaded platform 0.10 sec. after its release. if a further load of 400 kg is added to the platform, find, i) the frequency of damped vibrations, and i) the amplitude of vibration after 2 complete oscillations, given that the initial amplitude is 15 cm.
Answers: 1
image
Engineering, 04.07.2019 18:10, niyawilliams23
Asingle-geared blanking press has a stroke of 200 mm and a rated capacity of 320 kn. a cam driven ram is assumed to be capable of delivering the full press load at constant force during the last 15 percent of a constant-velocity stroke. the camshaft has an average speed of 90 rev/min and is geared to the flywheel shaft at a 6: 1 ratio. the total work done is to include an allowance of 16 percent for friction a) estimate the maximum energy fluctuation b) find the rim weight for an effective diameter of 1.2 m and a coefficient of speed fluctuation of 0.10
Answers: 1
image
Engineering, 04.07.2019 18:10, alyssabailey7545
Give heat transfer applications for the following, (i) gas turbines (propulsion) ) gas turbines (power generation). (iii) steam turbines. (iv) combined heat and power (chp). (v) automotive engines
Answers: 1
Do you know the correct answer?
A120 cy per hr maximum output pump is used to place the concrete for a 200 cy slab. the concrete is...