The dorben co. uses a standard hour plan with a base wage of $9.00/hour. it hires an ie consultant to plan a batch production run of 300 units. this consultant has a worker on the line produce two units. the first takes 10 minutes and the second 9.7 minutes.

a) find the equation of the learning curve?
b) what is the % learning?
c) how long would it take the worker to reach the standard time of 8.0 minutes
d) assume that the worker tries to improve and earn the incentive pay. what would the worker be paid for the first 20 hours under the standard-hour plan?
e) assuming that the worker continues to improve his performance, what will he be paid for the full batch of 300 units under the standard-hour plan?
f) what is the unit cost for the first unit made? what is the cost for 300th unit?

answer
Answers: 3

Other questions on the subject: Engineering

image
Engineering, 04.07.2019 18:10, sarahgrindstaff123
Afluid flows with a velocity field given by v=(x/t)i.. determine the local and convective accelerations when x=3 and t=1.
Answers: 2
image
Engineering, 04.07.2019 18:10, genyjoannerubiera
Assuming compressible flow of air and that the measurements are done at flagstaff a pitot static tube that gives the difference of total and static pressure measures 0.35 m of mercury. what is the velocity of air? assume the temperature to be 300k. (submit your excel or matlab calculation sheet)
Answers: 1
image
Engineering, 04.07.2019 18:10, QueenLife4869
Awall of 0.5m thickness is to be constructed from a material which has average thermal conductivity of 1.4 w/mk. the wall is to be insulated with a material having an average thermal conductivity of 0.35 w/mk so that heat loss per square meter shall not exceed 1450 w. assume inner wall surface temperature of 1200°c and outer surface temperature of the insulation to be 15°c. calculate the thickness of insulation required.
Answers: 3
image
Engineering, 04.07.2019 18:20, mjcbs21
What is the heat treatment of metals? what is the benefit of it? why and how it's useful? answer in details, do not write by hand.
Answers: 3
Do you know the correct answer?
The dorben co. uses a standard hour plan with a base wage of $9.00/hour. it hires an ie consultant t...

Questions in other subjects:

Konu
Mathematics, 08.02.2021 04:40
Konu
Mathematics, 08.02.2021 04:40