Engineering, 12.11.2019 07:31, joejoefofana
In a bid package given to a flooring sub, the gc accidently forgot to include a floor plan representing a few rooms totaling 2,500sf. the entire building is 550,000sf. the flooring subcontractor bid the project using the floorplans provided (missing 2,500sf) and signed a contract with the information received. if the scope of the contract states, "provide all flooring in new facility," is this contract enforceable by law? why or why not? 1.
Answers: 2
Engineering, 04.07.2019 18:10, ahmedeldyame
Aloaded platform of total mass 500 kg is supported by a dashpot and by a set of springs of effective stiffness 72 kn/m. it is observed that when the platform is depressed through a distance x = 12.5 cm below its equilibrium position and then released without any initial velocity; it reaches its equilibrium position in the shortest possible time without overshoot. find the position and velocity of the loaded platform 0.10 sec. after its release. if a further load of 400 kg is added to the platform, find, i) the frequency of damped vibrations, and i) the amplitude of vibration after 2 complete oscillations, given that the initial amplitude is 15 cm.
Answers: 1
Engineering, 04.07.2019 18:10, krystabrewer3
What are the two (02) benefits, which may result from a successful implementation of preventive maintenance (pm) program in an organization? (clo3)a)- lean manufacturing b)-overlapping responsibilities c)-the planner is not qualified d)-accurate contractor information e)-reduction in equipment redundancies f)-accurate stores information
Answers: 3
In a bid package given to a flooring sub, the gc accidently forgot to include a floor plan represent...