A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

answer
Answers: 2

Other questions on the subject: Computers and Technology

image
Computers and Technology, 22.06.2019 08:50, najashohatee1234
Can online classes such as gradpoint track your ip location like if im taking a final and i give somebody else my account and they take the final for me will it show where they are taking the final from? and can this be countered with a vpn
Answers: 1
image
Computers and Technology, 22.06.2019 16:00, raizagisselle1273
If a client wants to make minor edits, what should he/she use?
Answers: 3
image
Computers and Technology, 22.06.2019 19:00, dadonelson2109
If your accelerator suddenly gets stuck what should you do
Answers: 2
image
Computers and Technology, 23.06.2019 18:30, bsept1018
Report all segments of identity by descent longer than 20 polymorphisms between pairs of individuals in the following cohort of 15 individuals across 49 polymorphisms: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 numeric input 2 points possible (graded) you have 2 attempts to complete the assignment below. for example if the sequence is "bcd", which occurs in "abcdef" , the starting point would be 2 (b), and the finishing point would be 4(d). individuals 7,10 between positions
Answers: 1
Do you know the correct answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...

Questions in other subjects:

Konu
Mathematics, 06.03.2020 12:52
Konu
Mathematics, 06.03.2020 12:52