Computers and Technology

A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

Please answer fast

answer
Answers: 2

Other questions on the subject: Computers and Technology

image
Computers and Technology, 23.06.2019 09:00, 19youngr
Which company provides a crowdsourcing platform for corporate research and development? a: mtruk b: wiki answers c: mediawiki d: innocentive
Answers: 2
image
Computers and Technology, 23.06.2019 11:20, 1tzM3
Http is the protocol that governs communications between web servers and web clients (i. e. browsers). part of the protocol includes a status code returned by the server to tell the browser the status of its most recent page request. some of the codes and their meanings are listed below: 200, ok (fulfilled)403, forbidden404, not found500, server errorgiven an int variable status, write a switch statement that prints out the appropriate label from the above list based on status.
Answers: 2
image
Computers and Technology, 24.06.2019 02:30, sha273
Which option completes the explanation for conflict of interest in an organization
Answers: 1
image
Computers and Technology, 24.06.2019 11:00, abolton04
In three to five sentences, describe how you can organize written information logically and sequentially
Answers: 1
Do you know the correct answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...

Questions in other subjects:

Konu
English, 15.01.2021 21:00
Konu
Mathematics, 15.01.2021 21:00
Konu
Mathematics, 15.01.2021 21:00