In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

a. True.
b. False.

answer
Answers: 1

Other questions on the subject: Computers and Technology

image
Computers and Technology, 22.06.2019 00:00, ajwiebel3475
Which requirement is an appropriate reason for a business to use it tools
Answers: 3
image
Computers and Technology, 22.06.2019 18:30, Akkenson17871
The "instance" relationship shows that something is an object of a
Answers: 1
image
Computers and Technology, 23.06.2019 14:30, HarryPotter10
Open this link after reading about ana's situation. complete each sentence using the drop-downs. ana would need a minimum of ato work as a translator. according to job outlook information, the number of jobs for translators willin the future.
Answers: 3
image
Computers and Technology, 24.06.2019 23:30, binkyv15
Adrian has decided to subscribe for a new internet connection. he wants a high speed connection so that he can stream video content smoothly. which access technology would you advise adrian against using?
Answers: 1
Do you know the correct answer?
In assigning a value for the most pessimistic (b) duration, the project manager should estimate the...

Questions in other subjects:

Konu
Social Studies, 07.12.2020 21:40