If you have two tasks x and y, with y being a successor to x, if we mark x as undone (because it needs to be redone for some reason), then y will also need to be redone, as it might use the results of x.
To implement this, we will endow our scheduler with a redo method, which marks a task and any tasks that depend on it to be redone.

answer
Answers: 1

Other questions on the subject: Computers and Technology

image
Computers and Technology, 22.06.2019 16:30, mesposito
Technician a says that a dry sump system uses no oil storage sump under the engine. technician b says that a wet sump system uses no oil storage sump under the engine. who is correct?
Answers: 3
image
Computers and Technology, 23.06.2019 09:30, rscvsdfsrysas3712
Why is an outfitting a workspace with video games in a technology development company considered a strategic use of money
Answers: 1
image
Computers and Technology, 23.06.2019 23:30, jamalchris9353
Worth 50 points answer them bc i am not sure if i am wrong
Answers: 1
image
Computers and Technology, 25.06.2019 07:00, denisefaircloth73
Amisfire code is a type diagnostic trouble code (dtc).
Answers: 1
Do you know the correct answer?
If you have two tasks x and y, with y being a successor to x, if we mark x as undone (because it nee...

Questions in other subjects:

Konu
Physics, 18.07.2019 15:50