What is the critical path?
a. the path from resource to task that passes through all critica...
Computers and Technology, 03.12.2019 01:31, cadenm81
What is the critical path?
a. the path from resource to task that passes through all critical components of a project plan
b. the path between tasks to the projects finish that passes through all critical components of a project plan
c. the path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
d. the path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time
Answers: 3
Computers and Technology, 22.06.2019 12:10, drelisech6467
Linux is distributed under gnu gpl. why is this important? a. it ensures that only torvalds can profit from the sale of linux b. it prevents unknowledgeable users from downloading programs they don't know how to operate. c. it provides protection for the developers who created linux. d. it states that anyone can copy, modify, and share the program if changes are made public.
Answers: 1
Computers and Technology, 23.06.2019 15:00, puppylove899
Barbara is interested in pursuing a career in the science and math pathway. which qualifications will her reach that goal? a. an advanced knowledge of physics and math b. an advanced knowledge of engineering and math c. an advanced knowledge of physics and robotics an d. advanced knowledge of machinery and math
Answers: 1
Computers and Technology, 23.06.2019 21:30, maddietomlinson113
Examine the list below. which factors positively affect lifetime income? check all that apply.
Answers: 1
Advanced Placement (AP), 20.01.2021 19:40
Mathematics, 20.01.2021 19:40
Mathematics, 20.01.2021 19:40
History, 20.01.2021 19:40
Arts, 20.01.2021 19:40
History, 20.01.2021 19:40