Which of these statements regarding time-cost tradeoffs in cpm networks is true?
a. crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
b. crashing is not possible unless there are multiple critical paths.
c. crashing a project often reduces the length of long-duration, but noncritical, activities.
d. the crash time always exceeds the normal time.
e. activities not on the critical path can never be on the critical path, even after crashing.

answer
Answers: 1

Other questions on the subject: Computers and Technology

image
Computers and Technology, 22.06.2019 17:40, math31343
Gabe wants to move text from one document to another document. he should copy the text, paste the text, and open the new document highlight the text, select the cut command, move to the new document, make sure the cursor is in the correct location, and select the paste command select the save as command, navigate to the new document, and click save highlight the text, open the new document, and press ctrl and v
Answers: 1
image
Computers and Technology, 23.06.2019 03:00, SKYBLUE1015
What are the different parts of computer
Answers: 2
image
Computers and Technology, 23.06.2019 05:00, mikeysoulemison
Jason works as an accountant in a department store. he needs to keep a daily record of all the invoices issued by the store. which file naming convention would him the most?
Answers: 2
image
Computers and Technology, 24.06.2019 04:30, shadenShaden2037
What is the process in which the software development team compiles information to determine the final product
Answers: 1
Do you know the correct answer?
Which of these statements regarding time-cost tradeoffs in cpm networks is true?
a. crashing...

Questions in other subjects:

Konu
Physics, 25.10.2021 04:10
Konu
Chemistry, 25.10.2021 04:10
Konu
Mathematics, 25.10.2021 04:10