Joe and rich are both considering investing in a project that costs $25,500 and is expected to produce cash inflows of $15,800 in year 1 and $15,300 in year 2. joe has a required return of 8.5 percent but rich demands a return of 12.5 percent. who, if either, should accept this project? a. joe, but not rich b. rich, but not joe c. neither joe nor rich d. both joe and rich e. joe, and possibly rich, who will be neutral on this decision as his net present value will equal zero