Your project to obtain charitable donations is now 42 days into a planned 52-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 37 days of the project and to bring in $25,800. Even though we are 42 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is scheduled to run for 42 days starting on day 5 and extending through day 47. We estimate that, even though we should have (37/42) 88.10% of this activity complete, it is actually only 55% complete. This part of the project was scheduled to bring in $150,800 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $51,600. So far $179,000 has actually been brought in on the project a. Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index.
b. Find the following:a) Schedule Variance ($) =b) Scheudle Performance Index =c) Cost Variance ($) =d) Coster Performance Index =

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 16:00, paulonyemakonor549
2standard deviation a particular telephone number is used to receive both voice calls and fax messages. suppose that 25% of the incoming calls involve fax messages, and consider a sample of 25 incoming calls. (a) what is the expected number of calls among the 25 that involve a fax message?
Answers: 2
image
Business, 21.06.2019 21:40, Sarahinator04
This problem has been solved! see the answerchapter 19 problem #8. quality and financial control (connect, perform)part one: geometrica designs and builds domes and space frames for large buildings. while the company had developed quality standards over time to respond to different client problems and training needs, it lacked a unified quality system, and its global client base wanted assurance that geometrica met an established international standard for quality. which of the following was an appropriate step for this company to take? a) reform its accounting and financial reporting systems to comply with sarbanes-oxleyb) establish and document a quality management system to comply with iso 9000management at workyou are the new fleet manager at xpressship, a package delivery company. as your first project, your boss has asked that you to look into implementing an electronic monitoring system for the fleet of 2,000 trucks your company owns. a recent internal audit on maintenance and repair costs on the company’s vehicles revealed while maintenance was performed regularly on the trucks, mileage or use had not been taken into account. this resulted in approximately $20,000 of unneeded repairs. you know that telematics have been used by other companies with fleets of cars or trucks and it will allow your company to not only track mileage and use, but also part replacement needs, vehicle oil pressure, and drivers’ speed and real time location. tracking these items can reduce maintenance costs while improving efficiency. you find that a simple computer can be installed in each vehicle. when the drivers return at the end of the day, the telematics information from each vehicle will be uploaded to a master computer where a software program will generate a report with results on the variables you have selected. early one morning as you are getting a cup of coffee, a few drivers that have been with the company for many years approach you with some concerns. eldon, the most senior driver says, “i heard you’re installing some type of computer to track our driving. my buddy works over at parcel and post package delivery and he said they’ve got these computers, too. he said managers are writing people up and firing drivers for speeding or not wearing seat belts. are you going to do that to us, too? ”part two: as a manager, which of the following statements would be effective in maintaining a positive relationship with company drivers? check all that apply. a) at this time, xpressship will be using telematics to monitor maintenance and repair needs, not drivers’ motoring habitsb) although the company isn’t doing so now, when xpressship begins to monitor driver motoring habits, the company will encourage them to keep a separate daily log where they can document any unusual circumstancesc) while xpressship could monitor things like speed, location, and idle time, the company trusts their drivers and will not be using that data in disciplinary decisionsd) xpressship executives are happy with their technology and believe that implementation is ideal for your organization
Answers: 3
image
Business, 21.06.2019 22:00, cain1828
When slick heating company switched to an activity based costing system, it realized that it was allocating a much lower percentage of factory overhead to a product line that the marketing department was trying to push. the product line may contain which type of products?
Answers: 2
image
Business, 22.06.2019 11:00, hadwell34
You are attending college in the fall and you need to purchase a computer. you must finance the purchase because your parents will not purchase it for you, and you do not have the cash on hand to purchase it. in blank #1 determine which type of credit would you use to finance your purchase (installment, non-installment, or revolving credit). (2 points) in blank #2 defend your credit choice by explaining why your financing option is the best option for you. (2 points) in blank #3 explain why you selected that credit option over the other two options available. (2 points)
Answers: 3
Do you know the correct answer?
Your project to obtain charitable donations is now 42 days into a planned 52-day project. The projec...

Questions in other subjects:

Konu
Mathematics, 13.12.2021 04:00
Konu
Mathematics, 13.12.2021 04:00