Bill Fredlund, president of Lincoln Log Construction, is considering placing a bid on a building project. Bill has determined that five tasks would need to be performed to carry out the proj- ect. Using the PERT three-estimate approach, Bill has obtained the estimates in the next table for how long these tasks will take. Also shown are the precedence relationships for these tasks.
There is a penalty of $500,000 if the project is not completed in 11 weeks. Therefore, Bill is very interested in how likely it is that his company could finish the project in time.
(a) Construct the project network for this project. T
(b) Find the estimate of the mean and variance of the duration
of each activity.
(c) Find the mean critical path. T
(d) Find the approximate probability of completing the project
within 11 weeks.
Answers: 1
Business, 21.06.2019 18:10, diamondk2019
In a sumif conditional function, what should be the order of terms in the parentheses?
Answers: 1
Business, 22.06.2019 02:00, mckinley2006
What is an example of a good stock to buy in a recession? a) cyclical stock b) defensive stock c) income stock d) bond
Answers: 1
Business, 22.06.2019 08:10, nerdypineapple
What are the period and vertical shift of the cosecant function below? period: ; vertical shift: 1 unit up period: ; vertical shift: 2 units up period: ; vertical shift: 1 unit up period: ; vertical shift: 2 units up?
Answers: 3
Bill Fredlund, president of Lincoln Log Construction, is considering placing a bid on a building pro...
History, 11.02.2021 18:00
Mathematics, 11.02.2021 18:00