Bill Fredlund, president of Lincoln Log Construction, is considering placing a bid on a building project. Bill has determined that five tasks would need to be performed to carry out the proj- ect. Using the PERT three-estimate approach, Bill has obtained the estimates in the next table for how long these tasks will take. Also shown are the precedence relationships for these tasks. There is a penalty of $500,000 if the project is not completed in 11 weeks. Therefore, Bill is very interested in how likely it is that his company could finish the project in time.

(a) Construct the project network for this project. T

(b) Find the estimate of the mean and variance of the duration

of each activity.

(c) Find the mean critical path. T

(d) Find the approximate probability of completing the project

within 11 weeks.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 18:10, diamondk2019
In a sumif conditional function, what should be the order of terms in the parentheses?
Answers: 1
image
Business, 22.06.2019 02:00, mckinley2006
What is an example of a good stock to buy in a recession? a) cyclical stock b) defensive stock c) income stock d) bond
Answers: 1
image
Business, 22.06.2019 08:10, nerdypineapple
What are the period and vertical shift of the cosecant function below? period: ; vertical shift: 1 unit up period: ; vertical shift: 2 units up period: ; vertical shift: 1 unit up period: ; vertical shift: 2 units up?
Answers: 3
image
Business, 22.06.2019 17:30, Geo777
Four students are at an extracurricular activity fair at their high school and are trying to decide which clubs to join. some information about the students is listed in this chart: which describes which ctso each student should join?
Answers: 1
Do you know the correct answer?
Bill Fredlund, president of Lincoln Log Construction, is considering placing a bid on a building pro...

Questions in other subjects:

Konu
History, 11.02.2021 18:00