Activity-based costing for varying batch production A manufacturing company has the following two activities associated with completion of products:
The setting up of machines for running batches of products
The actual production of units produced
The company has annual manufacturing overhead costs of $2,000,000, of which $200,000 is directly involved in setting up machines for batch runs. During the year, the company expects to perform 400 machine setups, one setup per batch for a total of 400 batches of production. Assume that the batch sizes vary considerably, but the work involved in setting up the machines is not appreciably different from one job to the next.
If the company estimates that the $200,000 costs associated with setups will yield 400 setups this year, the cost associated directly with each setup will be $ per setup. Because each job will require its own setup, setup costs are viewed as batch costs. Because $200,000 of the $2,000,000 are costs associated with setups, this means that costs associated directly with the production of units equal $.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 21:30, ashl3yisbored
Gino's restaurant is a popular restaurant in boston, massachusetts. the owner of the restaurant has been trying to better understand costs at the restaurant and has hired a student intern to conduct an activity-based costing study. the intern, in consultation with the owner, identified the following major activities: activity cost pool activity measure serving a party of diners number of parties served serving a diner number of diners served serving drinks number of drinks ordered some costs, such as the cost of cleaning the linens that cover the restaurant's tables, vary with the number of parties served. other costs, such as washing plates and glasses, depends on the number of diners served or the number of drinks served. data concerning these activities are shown below. serving a party serving a dinner serving drinks total total cost $47,600 $153,000 $59,800 $260,400 total activity 7,000 parties 30,000 diners 46,000 drinks prior to the activity-based costing study, the owner knew very little about the costs of the restaurant. she knew that the total cost for the month was $260,400 and that 30,000 diners had been served. therefore, the average cost per diner was $8.68.required: 1. compute the activity rates for each of the three activities 2. according to the activity-based costing system, what is the total cost of serving each of the following parties of diners? a. a party of four diners who ordered three drinks in total b. a party of two diners who do not order any drinks c. a lone diner who orders two drinks 3. convert the total costs you computed in part (1) above to costs per diner. in other words, what is the average cost per diner for serving each of the following parties: a. a party of four diners who order three drinks in total b. a party of two diner who do not order any drinks c. a lone diner who orders two drinks 4. why do the costs per diner for the three different parties differ from each other and from the overall average coast of $9.80 per diner?
Answers: 1
image
Business, 22.06.2019 05:30, DragonWarrior203
From a business perspective, an information system provides a solution to a problem or challenge facing a firm and represents a combination of management, organization, and technology elements. the organization's hierarchy, functional specialties, business processes, culture, and political interest groups are components of which element of information systems?
Answers: 1
image
Business, 22.06.2019 08:40, Sk8terkaylee
Calculate the cost of each capital component—in other words, the after-tax cost of debt, the cost of preferred stock (including flotation costs), and the cost of equity (ignoring flotation costs). use both the capm method and the dividend growth approach to find the cost of equity. calculate the cost of new stock using the dividend growth approach. what is the cost of new common stock based on the capm? (hint: find the difference between re and rs as determined by the dividend growth approach and then add that difference to the capm value for rs.)assuming that gao will not issue new equity and will continue to use the same target capital structure, what is the company’s wacc? e. suppose gao is evaluating three projects with the following characteristics. each project has a cost of $1 million. they will all be financed using the target mix of long-term debt, preferred stock, and common equity. the cost of the common equity for each project should be based on the beta estimated for the project. all equity will come from reinvested earnings. equity invested in project a would have a beta of 0.5 and an expected return of 9.0%.equity invested in project b would have a beta of 1.0 and an expected return of 10.0%.equity invested in project c would have a beta of 2.0 and an expected return of 11.0%.analyze the company’s situation, and explain why each project should be accepted or rejected g
Answers: 1
image
Business, 22.06.2019 09:50, shanedawson19
Is exploiting a distinctive competence or improving efficiency for competitive advantage. (a) cooptation (b) coalition (c) competitive intelligence (d) competitive aggression (e) smoothing
Answers: 1
Do you know the correct answer?
Activity-based costing for varying batch production A manufacturing company has the following two...

Questions in other subjects:

Konu
History, 07.10.2019 21:00
Konu
English, 07.10.2019 21:00