Beginning and Ending Raw materials inventory 21000$. 35000$ respectively Beginning and Ending Work in Process inventory 17000$. 19000$ respectively
Finished Goods inventory 46000$, 38000$ respectively
Purchase of raw materials 76000$. Direct labor cost 83000$. Manufacturing overhead incurred 42000$
Indirect materials included in overhead cost incurred 6000$. Manufacturing overhead applied 44000$.
Cost of Goods Manufactured equals to
A. Another answer
B. 198000$
O c. 179000$
D. 185000$
E181000$

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 03:00, zahrast14
Which of the following is not a consideration when determining your asset allocation
Answers: 3
image
Business, 22.06.2019 10:20, Sparkledog
Blue spruce corp. has the following transactions during august of the current year. aug. 1 issues shares of common stock to investors in exchange for $10,170. 4 pays insurance in advance for 3 months, $1,720. 16 receives $710 from clients for services rendered. 27 pays the secretary $740 salary. indicate the basic analysis and the debit-credit analysis.
Answers: 1
image
Business, 22.06.2019 15:30, barstr9146
Brenda wants a new car that will be dependable transportation and look good. she wants to satisfy both functional and psychological needs. true or false
Answers: 1
image
Business, 22.06.2019 19:50, crzyemo865
Aproduction line has three machines a, b, and c, with reliabilities of .96, .86, and .85, respectively. the machines are arranged so that if one breaks down, the others must shut down. engineers are weighing two alternative designs for increasing the line’s reliability. plan 1 involves adding an identical backup line, and plan 2 involves providing a backup for each machine. in either case, three machines (a, b, and c) would be used with reliabilities equal to the original three. a. compute overall system reliability under plan 1. (round your intermediate calculations and final answer to 4 decimal places.) reliability b. compute overall system reliability under plan 2. (round your intermediate calculations and final answer to 4 decimal places.) reliability c. which plan will provide the higher reliability? plan2plan1
Answers: 3
Do you know the correct answer?
Beginning and Ending Raw materials inventory 21000$. 35000$ respectively Beginning and Ending Work...

Questions in other subjects:

Konu
Mathematics, 30.01.2020 21:00