Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finish-to-start relationships and that it might be possible to reduce project duration by creating start-to-start lags. After much deliberation the team concluded that the following relationships could be converted into start-to-start lags. • Procure prototype parts could start 6 days after the start of Design
• Fabricate parts could start 9 days after the start of Design
• Laboratory test could begin 1 day(s) after the start of Assemble prototype.
• Field test could start 6 days after the start of Laboratory test
• Adjust design could begin 7 days after the start of Field test.
• Order stock and Order custom components could begin 5 days and 5 days, respectively, after Adjust design
• Test unit could begin 9 days after the start of Assemble test production unit.
• Document results could start 3 days after the start of Test unit .
Reconfigure the cyclon schedule by entering all nine start-to-start Tags
What is the ES for Activity D?
What is the LF for Activity H?
What is the slack for Activity C?
What is the slack for Activity H?
What is the slack for Activity I?
What is the length of the project?
What is the critical path?

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 06:00, kinglightskin2k
If you miss two payments on a credit card what is generally the penalty
Answers: 1
image
Business, 22.06.2019 11:40, derrion67
During 2016, nike inc., reported net income of $3,760 million. the company declared dividends of $1,022 million. the closing entry for dividends would include which of the following? select one: a. credit cash for $1,022 million b. credit dividends for $1,022 million c. debit net income for $1,022 million d. credit retained earnings for $1,022 million e. debit dividends for $1,022 million
Answers: 1
image
Business, 22.06.2019 18:00, Aethis
Biochemical corp. requires $600,000 in financing over the next three years. the firm can borrow the funds for three years at 10.80 percent interest per year. the ceo decides to do a forecast and predicts that if she utilizes short-term financing instead, she will pay 7.50 percent interest in the first year, 12.15 percent interest in the second year, and 8.25 percent interest in the third year. assume interest is paid in full at the end of each year. a)determine the total interest cost under each plan. a) long term fixed rate: b) short term fixed rate: b) which plan is less costly? a) long term fixed rate plan b) short term variable rate plan
Answers: 2
image
Business, 22.06.2019 19:50, lucky1940
The common stock and debt of northern sludge are valued at $65 million and $35 million, respectively. investors currently require a return of 15.9% on the common stock and a return of 7.8% on the debt. if northern sludge issues an additional $14 million of common stock and uses this money to retire debt, what happens to the expected return on the stock? assume that the change in capital structure does not affect the interest rate on northern’s debt and that there are no taxes.
Answers: 2
Do you know the correct answer?
Management is not happy with the schedule and wants the project completed as soon as possible. Unfor...

Questions in other subjects:

Konu
Mathematics, 23.09.2021 09:10