Business, 10.08.2021 01:30, 60129

During week 1 of the plan, the bracket supplier notifies CFC that the order for 600 units will not arrive as planned. Instead, 300 will arrive this week and 300 will arrive next week, instead of all 600 arriving at the same time. Will this affects production and, if so, to what extent

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 03:00, arionaking59p71cfc
Match the given situations to the type of risks that a business may face while taking credit.(there's not just one answer)1. beta ltd. had taken a loan from a bankfor a period of 15 years, but its salesare gradually showing a decline.2. alpha ltd. has taken a loan for increasing its production and sales, but it has not conducted any researchbefore making this decision.3. delphi ltd. has an overseas client. the economy of the client’s country is going through severe recession.4. delphi ltd. has taken a short-term loanfrom the bank, but its supply chain logistics are not in place. a. foreign exchange riskb. operational riskc. term of loan riskd. revenue projections risk
Answers: 1
image
Business, 22.06.2019 17:00, kiahbryant12
Zeta corporation is a manufacturer of sports caps, which require soft fabric. the standards for each cap allow 2.00 yards of soft fabric, at a cost of $2.00 per yard. during the month of january, the company purchased 25,000 yards of soft fabric at $2.10 per yard, to produce 12,000 caps. what is zeta corporation's materials price variance for the month of january?
Answers: 2
image
Business, 22.06.2019 21:20, fespinoza019
Rediger inc., a manufacturing corporation, has provided the following data for the month of june. the balance in the work in process inventory account was $28,000 at the beginning of the month and $20,000 at the end of the month. during the month, the corporation incurred direct materials cost of $56,200 and direct labor cost of $29,800. the actual manufacturing overhead cost incurred was $53,600. the manufacturing overhead cost applied to work in process was $52,200. the cost of goods manufactured for june was:
Answers: 2
image
Business, 23.06.2019 00:00, destinyranson
Which of the following is not a factor to consider when deciding whether to accept a special order? whether this order will hurt the brand name of the company whether other potential orders would be more profitable whether additional fixed costs would need to be incurred whether the offered price is sufficient to cover prime costs and fixed overhead allocated all of the above
Answers: 2
Do you know the correct answer?
During week 1 of the plan, the bracket supplier notifies CFC that the order for 600 units will not a...